How do I install the WPS?
Follow the steps below to install the Wireless Ped System (WPS):
- Ensure proper signal quality between WPS and WPC
|
For connectivity:
- Ensure unobstructed line-of-sight between the antennas
- Ensure both antennas are at the same height
- Install the WPS between 5 and 20 ft from the signal head
|
- Plan out pole placement of WPS
|
The WPS must be positioned:
- Where its APS will be accessible to people with disabilities – see MUTCD 11 4I.05 or our Ultimate APS Application Guide for details
- At least 10 ft from any other APS to avoid confusion
- Near the curb ramp for its crosswalk
- Where it will be exposed to enough sunlight to keep the battery charged
|
- Install Polara Wireless Ped Head Control Unit (WPC)
|
The Wireless Ped Head Control Unit installs easily into pedestrian signal heads using the included hardware kit and external antenna:
- Drill a ÂĽ in hole in the ped head roof or floor for the antenna
- Attach the WPC unit to the mounting plate, and the mounting plate to the back of the ped head (if ped head does not already have tapped 1/4" holes, drill and tap holes to attach the mounting plate)
- Run jumper wires from the ped head’s terminal block (AC Neutral (ACN), Walk (WK), and Don’t Walk (DW)) to the unit’s input power terminal block, and attach the antenna
- At actuated intersections, connect the button wires to the Contact Closure terminals. The polarity of the button wires doesn’t matter.
- Record the serial number of the WPC and identify which Ped Head it is installed in. This information will be needed later.
- Close the ped head and restore power to it.
|
- Install pole
|
The optional Frey pole can install in less than 45 minutes on the existing sidewalk:
- Drill 5 in deep holes in sidewalk for anchor bolts
- Epoxy bolts into sidewalk
- Mount base to bolts and level
- Thread pipe into base
|
- Install iNS
|
- Drill and tap mounting holes and drill the wire pass-through hole
- Pass a 5 ft. section of the 16 ft. cable though the pass-through hole down into the base
- Mount the iNS backplate to the pole
- Install the iNS to the backplate and cable
|
- Install solar kit
|
- Attach the wedge casting to the solar kit body using the adhesive gasket and screws
- Thread bolts and wedge casting into pole casting
- Feed 11 ft. cable through solar kit and pole casting into pole, and install pole casting on pole with solar kit body oriented south.
- Assemble solar panel
- Attach battery harnesses to batteries and place batteries into solar kit, but do not connect harnesses to kit yet
- Connect 11 ft. and 5 ft. cables in pole base and close base cover
- Connect battery harnesses to solar kit, connect solar panel connectors to solar kit, and close solar kit lid.
|
- Set up WPS with Polara Field Service App
|
- Power the ped head
- Use the Field Service App to connect to the ped head control unit
- Change the default password and name of the control unit (the WPC will not operate until its password is changed to a non-default value)
- Use the Field Service App to connect to the solar kit
- Scan for control units that the solar kit can detect
- Select the control unit the solar kit should associate with
- Restart the solar kit and verify the iNS is working as intended
|
For complete information see the WPS install manual here.